Most of the cost and risk in an engine power station is fixed the day the plot is chosen. A site that looks convenient on a map can turn out to need a long access road for fuel tankers, piled foundations, a flood bund or an extra few spans of overhead line. Those items rarely appear in the first budget, yet they decide whether the station is built on time.

This guide sets out the criteria our engineers use when helping a mine or a utility choose where a heavy fuel oil or diesel station should go. It applies to stations from a few megawatts up to large multi-engine plants, and it ends with a simple way to compare candidate plots side by side.

Start from the load and the grid connection

For a mine, the station usually feeds a main intake substation near the processing plant. Every additional stretch of feeder between the generators and that substation adds cable or line cost, losses and a point of failure. For a utility plant, the question is how close the plot is to a substation with spare bay capacity and a transmission line able to carry the export.

Draw the single line from the station busbar to the point of supply before ranking any plot. If one site needs a new step-up transformer and line while another can connect at medium voltage through a short cable, that difference often outweighs everything else on the list. Our page on switchyard and grid connection work covers the electrical side in more depth.

Fuel delivery is a design input, not an afterthought

A heavy fuel oil station burns a steady volume of fuel every day, and that fuel arrives by road tanker, rail or pipeline. Map the route from the depot or port to each candidate plot. Look for bridge weight limits, steep grades, river crossings that close in the wet season and villages where tanker traffic will cause complaints.

Inside the boundary, the site needs space for an unloading bay, heated storage tanks inside a bund, day tanks and treatment equipment. HFO must be kept warm to stay pumpable, so a compact layout between storage and the engine hall saves on heat tracing. The arrangement of these elements is described in our guide to fuel farm design.

Ground conditions and drainage

Medium-speed engines are heavy and transmit vibration, so they sit on substantial concrete blocks. Weak clays, filled ground, shallow water tables or old mine workings can force piled foundations or ground improvement. A geotechnical investigation with boreholes at the engine hall, tank farm and transformer positions should be done before the site is fixed, not after.

Check flood history and the natural fall of the land. A plot in a low area may need raised platforms and a storm water system sized for heavy tropical rain. Spills from the fuel area must drain to an oil separator rather than to a river, which is easier to arrange on a site with a gentle, single-direction slope.

Cooling and water

Many engine stations use radiators, which need clean air and space but very little water. Even so, the site needs water for fuel treatment, engine washing, fire fighting and staff facilities. On a mine, the process water network may supply it; on a standalone utility plot, a borehole or a connection to a municipal main must be confirmed.

Hot, dusty or high sites reduce radiator performance and engine output. Record the ambient temperature range and the altitude of each candidate plot, because a site a few hundred metres higher or in a hot valley can change the number of engines needed for the same net output.

Wind, noise and neighbours

Engine exhausts, radiator fans and transformers produce noise and emissions that travel downwind. Place the station so the prevailing wind carries exhaust away from the mine camp, offices and nearby homes. A buffer of a few hundred metres to the nearest house removes a lot of expensive acoustic treatment and reduces the risk of a later complaint shutting units down at night.

Air quality permits often depend on stack height and distance to receptors, so the same plot decision affects the permit. It is far cheaper to move the station on the drawing than to add silencers and taller stacks once the hall is built.

Room to grow

Mines expand and utility demand rises. A good plot leaves space for more engines, a larger tank farm and additional transformer bays without moving the fence. Ideally the engine hall is laid out so that new units extend it in one direction, with the busbar and fuel headers sized for the final capacity.

That approach supports a staged build, where the first engines go in early and later ones follow as the load arrives. Our page on building a station in phases explains how to prepare foundations and switchgear for units that are not yet ordered.

Security, access and permits

Fuel stocks and copper cable attract theft, so the plot must be easy to fence, light and guard. Two access points help: one for heavy fuel and equipment deliveries and one for staff and emergency vehicles. Check land title, servitudes for lines and pipes, and any environmental or heritage constraints early, because a single unresolved claim can hold up the whole project.

For utility projects, the land and permit position is often a condition of the power purchase agreement and of finance. Lenders will ask for evidence that the site is secure and that the environmental assessment covered the plot that is actually being built on. Site risk is also shared out in the contract, which is one reason owners look at how a single EPC scope is organised before the plot is final.

A simple way to compare plots

List each candidate site in a table and score it against the criteria above: distance to load or substation, fuel route, ground, flood risk, water, noise buffer, expansion space, security and permit status. Weight the scores to reflect the project, for example giving fuel access more weight on a remote mine and grid connection more weight on a utility plant.

Add a rough cost for the items that differ between sites, such as extra line, piling or access road. The site with the best score is not always the cheapest, but the exercise makes the trade-offs visible to the owner, the lenders and the EPC contractor before money is committed.

About this guide

This guide comes from the USP&E power station design and site engineering team. USP&E is an EPC and O&M contractor, not a broker, with 150+ power projects in 45+ countries, 25,000 MW contracted since 2002 and 24+ years in the field. Our wider approach to heavy fuel stations is set out in the HFO station EPC and O&M overview.

Offices: Colorado Springs (1755 Telstar Dr, Suite 300), Knoxville (800 S Gay St, Suite 700), London (162-168 Regent Street), Johannesburg (22 Kildoon Rd, Bryanston), Cape Town (31 Brickfield Road, Woodstock) and China (No. 1 Ningzhou Road, Wuxi). Regions: USA | AFRICA | UK | UAE | CHINA. ISO 9001 and ISO 45001 certified.

Power station site selection questions

What matters most when choosing a power station site?

Distance to the load or substation and a reliable fuel delivery route usually matter most, followed by ground conditions, flood risk, noise buffer and room to expand.

Should an HFO station be close to the mine plant?

Close enough to keep the feeder short, but far enough that exhaust and noise do not reach the camp or offices. A few hundred metres downwind of sensitive areas is a common compromise.

Why is a geotechnical survey needed before the site is fixed?

Engine foundations are heavy and sensitive to settlement. Poor ground can add piling or ground improvement that changes the budget, so it should influence the choice of site.

How much spare land should be left for expansion?

Enough for the final planned number of engines, tank capacity and transformer bays, laid out so new units extend the hall in one direction without moving the fence.

Does the site affect the air permit?

Yes. Stack height and distance to homes and other receptors are central to most air quality assessments, so the plot choice directly affects permit conditions.

Compare your candidate sites

Send the coordinates of the plots you are considering, the load forecast and the fuel source, and our engineers will help score each site and flag the cost items that differ between them.

If a document set is easier than a conversation, send it to info@uspeglobal.com or upload a summary through the site review request form; to talk it over, dial +27 10 822 2324. Engines that can be packaged for a new station appear in our diesel generator listings.


Where we operate

USA | AFRICA | UK | UAE | CHINA

USP&E United States

Colorado Springs Office: 1755 Telstar Dr, Suite 300

Knoxville Office: 800 S Gay St, Suite 700

USP&E South Africa

Johannesburg Office: 22 Kildoon Rd, Bryanston

Cape Town Office: 31 Brickfield Road, Woodstock

USP&E United Kingdom

London Office: 162-168 Regent Street

USP&E China

China Office: No. 1, Ningzhou Road, Wuxi

Call:+27 10 822 2324  |  E:info@uspeglobal.com

ISO Certifications
ISO9001ISO45001

Powering Possibility. Built for the Frontier.
Full-service EPC & O&M. Not a broker.

© 2026 USP&E · Diesel Power Station is part of USP&E